It’s Friday!
We have had some crazy weather this week in Colorado with the #bombcyclone causing road shutdowns and delays on many job-sites. The snow did not stop all the progress though.
Check out this week’s work along with a couple pictures of the aftermath of the snow!
Apex Audiology – Ground-Up Project in Colorado Springs, Colorado
Our crew was able to get a lot done this week on the Apex job-site despite the snow we received here. The interior steel framing was completed along with the installation of wood framing beam pockets for exterior steel. We are using red iron structural and architectural steel for the exterior. Also, we were able to start pouring curbs and gutters. The rooftop curbs were framed and penetrations for mechanical made.
Gripstone – Ground-Up Project in Colorado Springs, Colorado
This week at Gripstone there was foundation prep with additional blankets and sand bags laid for the winter storm, but the snow did not stop our deliveries. We had nine semi loads of structural steel delivered and staged.
North Range Eye Care – Ground-Up in Commerce City, Colorado
NREC passed their electrical and framing inspections this week. Snow and having to clear snow delayed work.
Woodford – Ground-Up Project in Colorado Springs, Colorado
Woodford had crane rails installed and footers poured for retaining walls on the loading dock pad. We also dug trenches for poles and completed pipe runs. Lastly, we completed the installation of the HVAC system.